Project Description
Resurfacing of Airport Rd.
Resurfacing of Airport Rd
Client: Town of Hanover, NJ
OCC was contracted by the Township of Hanover to complete milling, and paving at Airport Rd., from the Columbia Turnpike to the End of Public Right of Way. Extra safety precautions and construction scheduling had to take place due to the nearby Morristown Airport to maintain safe flight travel in/out of the airport. OCC had also installed roughly ~300LF perforated HDPE pipe to supplement site drainage in a nearby swamp area.
Project Details
Contract Value
$217,291.91
Milling Area
12,900 SY
New Asphalt
1,500 Tons
HDPE Perforated Drainage Pipe
340 LF
Reconstructed Type B Inlets:
3
Polymerized Joint Adhesive
10,000 LF